2x1MWp PV Power Plant Feasibility & Interconnection Study in Manokwari, West Papua

//2x1MWp PV Power Plant Feasibility & Interconnection Study in Manokwari, West Papua
2x1MWp PV Power Plant Feasibility & Interconnection Study in Manokwari, West Papua2025-11-14T07:35:09+00:00

Project Description

Application for 2x1MWp PV :

  • Field data measurement
  • Existing power system data collection & modelling
  • PV Plant modelling
  • Load flow & Short circuit simulation
  • Transient simulation
  • Quasi-Dynamic simulation
  • Protection analysis
  • Power plant design

Scope of work:

  • Feasibility study
  • Interconnection study
  • Detailed engineering design

Technology:

  • HOMER Pro
  • DIgSILENT Power factory
  • ETAP
  • AutoCAD

LOCATION

Manokwari, West Papua

CLIENT

PT. Surya Energi Indotama

END CLIENT

Kementrian ESDM

PROJECT YEAR

2018