Syntek Energy & Control has been tasked by PT PLN (Persero) to integrate SCADA systems at 22 Substations scattered across the South, Southeast, and West Sulawesi regions. Remote Terminal Units (RTUs) were successfully installed in July 2023, enhancing the reliability of the 20kV distribution network.
With the installation of these facilities, PLN UP2D SULSELRABAR can respond quickly to handle and restore power outages caused by disturbances, thus efficiently addressing blackouts.
Syntek Energy & Control proudly continues to be entrusted by PT PLN (Persero) to design, install, and commission SCADAtel devices to enhance the overall reliability of the network.