Project Description
Application:
- Sootblowing process for boiler in PLN Ombilin Coal Power Plant
Sootblowing PLC Scope of work:
- Siemens PLC replacement and reprogramming
- Migration from Operator Panel to Intouch HMI
Technology:
- Siemens S5 to S7-300 with TIA Portal v14
- Hilscher NetLink NL50-MPI (MPI Ethernet Gateway)
- IBHnet OPC Server
- Wonderware Intouch HMI and FSGateway
LOCATION
Sawahlunto,Padang
END CLIENT
PLN Ombilin
PROJECT YEAR
2017