Project Description

Syntek Energy & Control has been assigned by PT PLN (Persero) UP2D Riau to integrate SCADA systems
into the feeder bays across 6 locations in the Riau region. The Remote Terminal Unit (RTU) was successfully installed in December 2022.

Despite facing challenges such as narrow cable pathways and inflexible scheduling due to power outage schedules from the Main Substation,
the Syntek team managed to complete the work effectively within the designated timeframe. Upon completion,
PLN operators or maintenance teams can remotely and in real-time monitor and control the operation of feeder bays from the PLN SCADA Master Station interface.

Syntek Energy & Control takes great pride in consistently being entrusted by PLN to design, install, and commission SCADA devices to enhance public service.